Scheduled time period
Wednesday 5th July 2017 at 1:00am to Thursday 6th July 2017 at 11:00amCygnus field production reduction due to pipeline inspection pigging program
Unavailable Capacity
3.5mcm/d
Available Capacity
3.5mcm/d
Technical Capacity
7mcm/d