This is not the latest revision of this event. Please click here to see the latest update.

Scheduled time period

Wednesday 5th July 2017 at 1:00am to Thursday 6th July 2017 at 11:00am

Cygnus field production reduction due to pipeline inspection pigging program

Unavailable Capacity
3.5mcm/d
Available Capacity
3.5mcm/d
Technical Capacity
7mcm/d
Further Information