Scheduled time period
Sunday 30th July 2017 at 6:00pm to Wednesday 6th September 2017 at 6:00amA 2 day ramp up to normal rates is forecast to commence on the 6th September 2017
Due to delay estimated restart is now 6th September 2017.
Related Remits
Below is a list of the other remits that belong to the same event as the remit above.
Scheduled time period
Sunday 30th July 2017 at 6:00pm to Tuesday 19th September 2017 at 6:00pmA 2 day ramp up to normal rates within 48 hours.
Offshore production has restarted and ramp-up is in progress.
Scheduled time period
Sunday 30th July 2017 at 6:00pm to Tuesday 19th September 2017 at 3:00pmA 2 day ramp up to normal rates is expected to commence from the 19th September 2017
Start-up is in progress.
Scheduled time period
Sunday 30th July 2017 at 6:00pm to Monday 18th September 2017 at 6:00pmA 2 day ramp up to normal rates is forecast to commence on the 18th September 2017
Due to delay estimated restart is now 18th September 2017.
Scheduled time period
Sunday 30th July 2017 at 6:00pm to Sunday 17th September 2017 at 6:00pmA 2 day ramp up to normal rates is forecast to commence on the 17th September 2017
Due to delay estimated restart is now 17th September 2017.
Scheduled time period
Sunday 30th July 2017 at 6:00pm to Friday 15th September 2017 at 6:00pmA 2 day ramp up to normal rates is forecast to commence on the 15th September 2017
Due to delay estimated restart is now 15th September 2017.
Scheduled time period
Sunday 30th July 2017 at 6:00pm to Thursday 14th September 2017 at 6:00amA 2 day ramp up to normal rates is forecast to commence on the 14th September 2017
Due to delay estimated restart is now 14th September 2017.
Scheduled time period
Sunday 30th July 2017 at 6:00pm to Tuesday 12th September 2017 at 6:00amA 2 day ramp up to normal rates is forecast to commence on the 12th September 2017
Due to delay estimated restart is now 12th September 2017.
Scheduled time period
Sunday 30th July 2017 at 6:00pm to Friday 25th August 2017 at 6:00amA 2 day ramp up to normal rates is forecast to commence on the 25th August 2017
Offshore production has stopped earlier than forecast.
Scheduled time period
Monday 31st July 2017 at 6:00am to Saturday 26th August 2017 at 6:00am2 day ramp up to normal rates will commence on the 26th August 2017
Ramp down of flows commencing 30th July 2017