This is not the latest revision of this event. Please click here to see the latest update.

Scheduled time period

Sunday 30th July 2017 at 6:00pm to Friday 15th September 2017 at 6:00pm

A 2 day ramp up to normal rates is forecast to commence on the 15th September 2017

Due to delay estimated restart is now 15th September 2017.

Unavailable Capacity
11mcm/d
Available Capacity
0mcm/d
Technical Capacity
11mcm/d
Further Information