Scheduled time period

Sunday 30th July 2017 at 6:00pm to Tuesday 19th September 2017 at 3:00pm

A 2 day ramp up to normal rates is expected to commence from the 19th September 2017

Start-up is in progress.

Unavailable Capacity
11mcm/d
Available Capacity
0mcm/d
Technical Capacity
11mcm/d
Further Information