Notification History
Notification History
Scheduled time period
Wednesday 3rd June 2026 at 7:00am to Wednesday 3rd June 2026 at 7:00pmReduction in flow to 0 Mm3/d for duration
12 hour plant outage for ESD/TPS testing
Impacted time period
Monday 15th December 2025 at 10:00pm to Tuesday 16th December 2025 at 6:00amElgin Franklin flows at Bacton SEAL to restart at 2200 and slowly ramp up over the remainder of the gas day
Impacted time period
Monday 15th December 2025 at 5:00pm to Tuesday 16th December 2025 at 6:00amElgin Franklin gas export stopped, flows at the Bacton SEAL terminal are forecast to go to zero from 1700. Elgin Franklin flows at Perenco terminal to reduce by approx 1.7 MCM/D at the same time.
Impacted time period
Friday 12th December 2025 at 5:35pm to Friday 12th December 2025 at 9:20pmReduced Perenco Bacton throughput due to unplanned onshore outage. Restart now complete with throughput back to previous rate.
Perenco Bacton terminal shutdown
Impacted time period
Friday 12th December 2025 at 5:35pm to Friday 12th December 2025 at 10:00pmReduced Perenco Bacton throughput due to unplanned onshore outage. Restart ongoing with throughput increasing to previous rate.
Perenco Bacton terminal shutdown
Impacted time period
Friday 12th December 2025 at 5:35pm to Friday 12th December 2025 at 8:35pmReduced Perenco Bacton throughput due to unplanned onshore outage. Restart now ongoing with throughput increasing to previous rate.
Perenco Bacton terminal shutdown
Impacted time period
Friday 12th December 2025 at 5:35pm to Friday 12th December 2025 at 8:35pmReduced Perenco Bacton throughput due to unplanned onshore outage.
Perenco Bacton terminal shutdown
Impacted time period
Friday 12th December 2025 at 10:23am to Friday 12th December 2025 at 6:00pmReduced Perenco Bacton throughput due to unplanned onshore outage. Restart now complete with throughput increasing to previous rate.
Perenco Bacton terminal shutdown
Impacted time period
Friday 12th December 2025 at 10:23am to Friday 12th December 2025 at 6:00pmReduced Perenco Bacton throughput due to unplanned onshore outage. Restart now complete with throughput increasing to previous rate.
Perenco Bacton terminal shutdown
Impacted time period
Friday 12th December 2025 at 10:23am to Friday 12th December 2025 at 6:00pmReduced Perenco Bacton throughput due to unplanned onshore outage. Restart now underway.
Perenco Bacton terminal shutdown