Notification History

Scheduled time period

Wednesday 3rd June 2026 at 7:00am to Wednesday 3rd June 2026 at 7:00pm

Reduction in flow to 0 Mm3/d for duration

12 hour plant outage for ESD/TPS testing

Unavailable Capacity
38mcm/d
Available Capacity
7mcm/d
Technical Capacity
45mcm/d
Further Information

Impacted time period

Monday 15th December 2025 at 10:00pm to Tuesday 16th December 2025 at 6:00am

Elgin Franklin flows at Bacton SEAL to restart at 2200 and slowly ramp up over the remainder of the gas day

Unavailable Capacity
1.6mcm/d
Available Capacity
3mcm/d
Technical Capacity
4.6mcm/d
Further Information

Impacted time period

Monday 15th December 2025 at 5:00pm to Tuesday 16th December 2025 at 6:00am

Elgin Franklin gas export stopped, flows at the Bacton SEAL terminal are forecast to go to zero from 1700. Elgin Franklin flows at Perenco terminal to reduce by approx 1.7 MCM/D at the same time.

Unavailable Capacity
4.6mcm/d
Available Capacity
0mcm/d
Technical Capacity
4.6mcm/d
Further Information

Impacted time period

Friday 12th December 2025 at 5:35pm to Friday 12th December 2025 at 9:20pm

Reduced Perenco Bacton throughput due to unplanned onshore outage. Restart now complete with throughput back to previous rate.

Perenco Bacton terminal shutdown

Unavailable Capacity
0mcm/d
Available Capacity
8.2mcm/d
Technical Capacity
8.2mcm/d
Further Information

Impacted time period

Friday 12th December 2025 at 5:35pm to Friday 12th December 2025 at 10:00pm

Reduced Perenco Bacton throughput due to unplanned onshore outage. Restart ongoing with throughput increasing to previous rate.

Perenco Bacton terminal shutdown

Unavailable Capacity
1.2mcm/d
Available Capacity
7mcm/d
Technical Capacity
8.2mcm/d
Further Information

Impacted time period

Friday 12th December 2025 at 5:35pm to Friday 12th December 2025 at 8:35pm

Reduced Perenco Bacton throughput due to unplanned onshore outage. Restart now ongoing with throughput increasing to previous rate.

Perenco Bacton terminal shutdown

Unavailable Capacity
4.2mcm/d
Available Capacity
4mcm/d
Technical Capacity
8.2mcm/d
Further Information

Impacted time period

Friday 12th December 2025 at 5:35pm to Friday 12th December 2025 at 8:35pm

Reduced Perenco Bacton throughput due to unplanned onshore outage.

Perenco Bacton terminal shutdown

Unavailable Capacity
7.2mcm/d
Available Capacity
1mcm/d
Technical Capacity
8.2mcm/d
Further Information

Impacted time period

Friday 12th December 2025 at 10:23am to Friday 12th December 2025 at 6:00pm

Reduced Perenco Bacton throughput due to unplanned onshore outage. Restart now complete with throughput increasing to previous rate.

Perenco Bacton terminal shutdown

Unavailable Capacity
1mcm/d
Available Capacity
6.2mcm/d
Technical Capacity
7.2mcm/d
Further Information

Impacted time period

Friday 12th December 2025 at 10:23am to Friday 12th December 2025 at 6:00pm

Reduced Perenco Bacton throughput due to unplanned onshore outage. Restart now complete with throughput increasing to previous rate.

Perenco Bacton terminal shutdown

Unavailable Capacity
1mcm/d
Available Capacity
6.2mcm/d
Technical Capacity
7.2mcm/d
Further Information

Impacted time period

Friday 12th December 2025 at 10:23am to Friday 12th December 2025 at 6:00pm

Reduced Perenco Bacton throughput due to unplanned onshore outage. Restart now underway.

Perenco Bacton terminal shutdown

Unavailable Capacity
7.2mcm/d
Available Capacity
0mcm/d
Technical Capacity
7.2mcm/d
Further Information

Refine By

See our archive for events before Dec 2016