Notification History

Scheduled time period

Thursday 10th September 2026 at 4:59am to Thursday 17th September 2026 at 4:59am

Annual Maintenance - Export System

Unavailable Capacity
67GWh/d
Available Capacity
0GWh/d
Technical Capacity
67GWh/d
Further Information

Scheduled time period

Wednesday 2nd September 2026 at 5:00am to Thursday 10th September 2026 at 4:59am

Annual Maintenance - Import and Export System Unavailable

Unavailable Capacity
89GWh/d
Available Capacity
0GWh/d
Technical Capacity
89GWh/d
Further Information

Scheduled time period

Thursday 9th July 2026 at 6:00am to Friday 10th July 2026 at 6:00pm

"Publications according to article 4(1) of REMIT Disclaimer Any disclosures that are set out on this page are made pursuant to Regulation (EU) 1227/2011. They are based on the information that is available at the time of publication and are provided on a reasonable endeavours basis. A notification will be made of any material changes to these disclosures. We accept no liability for the content should it subsequently be demonstrated to be inaccurate. If you have any queries regarding this publication, please contact HST@spirit-energy.com"

Planned Terminal Maintenance

Unavailable Capacity
6mcm/d
Available Capacity
0mcm/d
Technical Capacity
6mcm/d
Further Information

Scheduled time period

Sunday 10th May 2026 at 2:00am to Monday 6th July 2026 at 10:00pm

"Publications according to article 4(1) of REMIT Disclaimer Any disclosures that are set out on this page are made pursuant to Regulation (EU) 1227/2011. They are based on the information that is available at the time of publication and are provided on a reasonable endeavours basis. A notification will be made of any material changes to these disclosures. We accept no liability for the content should it subsequently be demonstrated to be inaccurate. If you have any queries regarding this publication, please contact HST@spirit-energy.com"

Planned Annual Terminal Maintenance

Unavailable Capacity
6mcm/d
Available Capacity
0mcm/d
Technical Capacity
6mcm/d
Further Information

Impacted time period

Tuesday 30th June 2026 at 12:00am to Tuesday 30th June 2026 at 9:00am

Elgin-Franklin gas export has restarted flows are currently ramping up. Deliveries at Bacton SEAL to start from midnight.

Unavailable Capacity
2mcm/d
Available Capacity
2.5mcm/d
Technical Capacity
4.5mcm/d
Further Information

Impacted time period

Thursday 25th June 2026 at 12:00pm to Tuesday 30th June 2026 at 12:00pm

Elgin-Franklin gas export has restarted flows are currently ramping up. Restart of delivery at Bacton SEAL expected to being overnight.

Unavailable Capacity
4.5mcm/d
Available Capacity
0mcm/d
Technical Capacity
4.5mcm/d
Further Information

Scheduled time period

Monday 29th June 2026 at 10:00am to Monday 29th June 2026 at 2:00pm

Train 2 - R HTR MTC

Planned Outage

Unavailable Capacity
66.98GWh/d
Available Capacity
220.8GWh/d
Technical Capacity
287.78GWh/d
Further Information

Scheduled time period

Thursday 30th April 2026 at 8:00am to Tuesday 7th July 2026 at 5:00pm

Outage extended for Essential maintenance

Planned Outage/Restriction

Unavailable Capacity
27GWh/d
Available Capacity
0GWh/d
Technical Capacity
27GWh/d
Further Information

Scheduled time period

Thursday 30th April 2026 at 8:00am to Tuesday 7th July 2026 at 5:00pm

Outage extended for Essential maintenance

Planned Outage/Restriction

Unavailable Capacity
20GWh/d
Available Capacity
0GWh/d
Technical Capacity
20GWh/d
Further Information

Scheduled time period

Monday 19th October 2026 at 5:00am to Friday 23rd October 2026 at 6:00pm

GC-1 outage.

Planned Outage

Unavailable Capacity
97.78GWh/d
Available Capacity
195.55GWh/d
Technical Capacity
293.33GWh/d
Further Information