Notification History

Scheduled time period

Sunday 19th September 2021 at 12:00pm to Wednesday 22nd September 2021 at 12:00pm

Perenco Bacton reduced terminal throughput.

Perenco Bacton reduced terminal throughput due to planned offshore outage.

Unavailable Capacity
11mcm/d
Available Capacity
1mcm/d
Technical Capacity
12mcm/d
Further Information

Scheduled time period

Sunday 19th September 2021 at 12:00pm to Wednesday 22nd September 2021 at 12:00pm

Planned offshore maintenance

Unavailable Capacity
7.93mcm/d
Available Capacity
0mcm/d
Technical Capacity
7.93mcm/d
Further Information

Scheduled time period

Saturday 18th September 2021 at 6:00pm to Tuesday 21st September 2021 at 12:00pm

Perenco Bacton reduced terminal throughput.

Perenco Bacton reduced terminal throughput due to planned offshore outage.

Unavailable Capacity
11mcm/d
Available Capacity
1mcm/d
Technical Capacity
12mcm/d
Further Information

Scheduled time period

Saturday 18th September 2021 at 6:00pm to Tuesday 21st September 2021 at 12:00pm

Planned offshore maintenance

Unavailable Capacity
7.93mcm/d
Available Capacity
0mcm/d
Technical Capacity
7.93mcm/d
Further Information

Scheduled time period

Friday 3rd September 2021 at 6:00am to Friday 24th September 2021 at 6:00am

Perenco Dimlington Terminal . Throughput has been reduced from approx. 0300hrs from offshore in preparation for the annual shutdown to commence from 0600hrs on the 3rd. Onshore elements are expected to conclude on the 17th September allowing a partial return to production (some 70-90mmscf estimate) during the final week of the REMIT post. Dimlington Terminal Export ceased at 0540hrs for the commencement of planned onshore and offshore activities. Onshore elements are expected to conclude on the 17th September allowing a partial return to production (some 70-90mmscf estimate). Latest update. The Terminal shutdown is slightly ahead of schedule. There is a chance of some partial production during the night shift of gas day 15th. Estimated between 50 - 70mmscf. Update: Dimlington Terminal commenced Export from 2105hrs. Partial production available approx. 70mmscf. Update: Offshore production has increased further within gas day 17th. Current production available approx. 95mmscf.

Perenco Dimlington Terminal reduced Throughput due to the planned annual shutdown

Unavailable Capacity
5.5mcm/d
Available Capacity
0mcm/d
Technical Capacity
5.5mcm/d
Further Information

Scheduled time period

Monday 15th November 2021 at 5:00am to Monday 29th November 2021 at 5:00pm

To carry outr planned wireline maintenance

Essential Maintenance

Unavailable Capacity
20GWh/d
Available Capacity
0GWh/d
Technical Capacity
20GWh/d
Further Information

Scheduled time period

Monday 15th November 2021 at 5:00am to Wednesday 29th December 2021 at 5:00pm

To carry out planned wireline maintenance

Essential Maintenance

Unavailable Capacity
27GWh/d
Available Capacity
0GWh/d
Technical Capacity
27GWh/d
Further Information

Impacted time period

Thursday 16th September 2021 at 12:00pm to Friday 17th September 2021 at 6:00am

Culzean flows ramping up.

Unavailable Capacity
25GWh/d
Available Capacity
132GWh/d
Technical Capacity
157GWh/d
Further Information

Scheduled time period

Saturday 18th September 2021 at 12:00pm to Tuesday 21st September 2021 at 12:00pm

Perenco Bacton reduced terminal throughput.

Perenco Bacton reduced terminal throughput due to planned offshore outage.

Unavailable Capacity
11mcm/d
Available Capacity
1mcm/d
Technical Capacity
12mcm/d
Further Information

Scheduled time period

Saturday 18th September 2021 at 12:00pm to Tuesday 21st September 2021 at 12:00pm

Planned offshore maintenance

Unavailable Capacity
7.93mcm/d
Available Capacity
0mcm/d
Technical Capacity
7.93mcm/d
Further Information

Refine By

See our archive for events before Dec 2016