This is not the latest revision of this event. Please click here to see the latest update.
Further Information
Scheduled time period
Monday 24th February 2020 at 8:00am to Monday 24th February 2020 at 4:00pmGas Turbine/Compressor not available to Export, shutdown for Maintenance work
Gas Compressor bearing RTD to be changed
Unavailable Capacity
20000GWh/d
Available Capacity
0GWh/d
Technical Capacity
20000GWh/d