This is not the latest revision of this event. Please click here to see the latest update.

Impacted time period

Friday 23rd September 2022 at 6:00pm to Saturday 24th September 2022 at 6:00am

Elgin Franklin gas export has stopped, fault has been identified and restart process is underway. Gas Delivery from Bacton SEAL is currently forecast to go to zero at 1800 today. Approx. 2.0 MCM/D of Elgin Frankin gas is being delivered into the Perenco terminal, this is forecast to stop at 1800 also.

Unavailable Capacity
9mcm/d
Available Capacity
0mcm/d
Technical Capacity
9mcm/d
Further Information