Scheduled time period

Monday 20th March 2023 at 6:00am to Friday 19th May 2023 at 6:00pm

Reduced Perenco Bacton terminal gas export.

Unplanned onshore transmission system unavailability. Onshore maintenance complete, PUK Bacton deliveries continuing to increase through the morning.

Unavailable Capacity
4.3mcm/d
Available Capacity
8mcm/d
Technical Capacity
12.3mcm/d