Impacted time period

Thursday 18th May 2023 at 5:00pm to Saturday 20th May 2023 at 5:00am

Due to the unplanned unavailability of the Avonbridge compressor station as of 17:00 18/05/2023. St Fergus terminal flows are likely to be impacted. Current firm entitlements remain unaffected. National Gas Transmission will provide further updates as the issue is resolved.

Unplanned Compressor unavailability at Avonbridge.

Unavailable Capacity
576000000KWh/d
Available Capacity
744000000KWh/d
Technical Capacity
1500000000KWh/d