Scheduled time period

Tuesday 1st August 2023 at 6:00am to Thursday 17th August 2023 at 6:00am

Partial production expected to resume 16/08/23 00:00 with ramp up to previous rates over the course of the morning.

Perenco Bacton reduced throughput due to planned maintenance activities.

Unavailable Capacity
7.5mcm/d
Available Capacity
5.5mcm/d
Technical Capacity
13mcm/d