Impacted time period

Wednesday 17th April 2024 at 5:00pm to Monday 22nd April 2024 at 3:00pm

Main 12" gas pipeline blocked. Not possible to Import or Export any gas until 12" pipeline cleaning operations are complete.

Main 12" gas pipeline blocked. Not possible to Import or Export any gas.

Unavailable Capacity
20GWh/d
Available Capacity
0GWh/d
Technical Capacity
20GWh/d