Impacted time period
Wednesday 23rd January 2019 at 12:00pm to Friday 25th January 2019 at 12:00pmA delay in restarting production
Elgin Franklin restart process is underway. Gas export from Elgin Franklin is not expected until late tonight. Gas Delivery at Bacton SEAL for Elgin Franklin is not expected until very late on Gas Day 24th January or more likely early Gas Day 25th January
Unavailable Capacity
11mcm/d
Available Capacity
0mcm/d
Technical Capacity
11mcm/d