This is not the latest revision of this event. Please click here to see the latest update.

Scheduled time period

Sunday 27th April 2025 at 9:00am to Tuesday 29th April 2025 at 6:00am

Elgin Franklin production will cease due to a planned rig move. Flows from Bacton SEAL will stop at 09:00hrs. Approximately 2 MCM/D of Elgin Franklin gas is being delivered at the Bacton Perenco terminal, this will also stop.

Unavailable Capacity
4.9mcm/d
Available Capacity
0mcm/d
Technical Capacity
4.9mcm/d
Further Information