This is not the latest revision of this event. Please click here to see the latest update.
Further Information
Impacted time period
Tuesday 29th April 2025 at 8:00pm to Thursday 1st May 2025 at 6:00amCulzean has restarted and will continue to ramp up over the gas-day.
Unavailable Capacity
92GWh/d
Available Capacity
30GWh/d
Technical Capacity
122GWh/d