Impacted time period

Thursday 31st July 2025 at 5:29pm to Saturday 31st January 2026 at 5:29pm

The CHP gas turbine (9G-1) at PLOR will be taken off-line and will remain off-line . This is due to the reducing electrical demand of the refinery as process units shut down and the limits on export capacity. It means that we will move from an export position (19MW export) to an import position (approx. ~ 14MW import). The import will reduce gradually over the next ~ 10 days as units come off. There is no end date.