Impacted time period
Friday 21st November 2025 at 4:43pm to Tuesday 31st March 2026 at 6:00pmGC-2 Outage
Failure
Unavailable Capacity
144.45GWh
Available Capacity
148.88GWh
Technical Capacity
293.33GWh
Related Remits
Below is a list of the other remits that belong to the same event as the remit above.
Impacted time period
Friday 21st November 2025 at 4:43pm to Tuesday 17th March 2026 at 5:00amGC-2 Outage
Failure
Unavailable Capacity
144.45GWh/d
Available Capacity
148.88GWh/d
Technical Capacity
293.33GWh/d
Impacted time period
Friday 21st November 2025 at 4:43pm to Tuesday 17th March 2026 at 5:00amGC-2 Outage
Failure
Unavailable Capacity
144.45GWh/d
Available Capacity
148.88GWh/d
Technical Capacity
293.33GWh/d
Impacted time period
Friday 21st November 2025 at 4:43pm to Thursday 8th January 2026 at 6:00pmGC-2 Outage
Failure
Unavailable Capacity
144.45GWh
Available Capacity
148.88GWh
Technical Capacity
293.33GWh
Impacted time period
Friday 21st November 2025 at 4:43pm to Wednesday 17th December 2025 at 6:00pmGC-2 Outage
Failure
Unavailable Capacity
144.45GWh
Available Capacity
148.88GWh
Technical Capacity
293.33GWh
Impacted time period
Friday 21st November 2025 at 4:43pm to Wednesday 10th December 2025 at 6:00pmGC-2 Outage
Failure
Unavailable Capacity
144.45GWh
Available Capacity
148.88GWh
Technical Capacity
293.33GWh
Impacted time period
Friday 21st November 2025 at 3:43pm to Wednesday 3rd December 2025 at 5:00amGC-2 Outage
Failure
Unavailable Capacity
144.45GWh
Available Capacity
148.88GWh
Technical Capacity
293.33GWh
Impacted time period
Saturday 22nd November 2025 at 5:00am to Wednesday 3rd December 2025 at 5:00amGC-2 Outage
Failure
Unavailable Capacity
144.45GWh
Available Capacity
148.88GWh
Technical Capacity
293.33GWh