This is not the latest revision of this event. Please click here to see the latest update.
Further Information
Impacted time period
Wednesday 7th January 2026 at 2:53am to Wednesday 7th January 2026 at 4:59amDue to an unplanned reduction in capability through the Wormington Compressor station as of 02:53 on 07th January, users will experience a restriction in end of day volumes that can be accommodated at the Milford Haven Aggregated System Entry Point (ASEP) for the current gas day until 05:00 7th January. National Gas Transmission shall continue to provide updates until the issue is resolved.
Reduced transmission capability at Wormington Compressor Station
Unavailable Capacity
95GWh/d
Available Capacity
865GWh/d
Technical Capacity
950GWh/d