Impacted time period
Monday 26th January 2026 at 8:30pm to Thursday 29th January 2026 at 11:00pmReduced flow capability to Stallingborough 1 Power Station (South Humber Bank Phase 1) for a duration of approximately 3 days. NG shall continue to provide updates until the issue is resolved.
Due to a local asset issue on the National Gas network at Stallingborough Power Station we are unable to support supplies to Stallingborough 1 Power Station (South Humber Bank Phase 1). National Gas will continue to support uninterrupted supplies to Stallingborough 2 Power Station.
Unavailable Capacity
3.7mcm/d
Available Capacity
2.6mcm/d
Technical Capacity
6.3mcm/d