This is not the latest revision of this event. Please click here to see the latest update.

Impacted time period

Wednesday 28th October 2026 at 5:36pm to Wednesday 28th October 2026 at 11:59pm

Terminal flow currently at Zero, Forward flow now from the Terminal, expected to ramp up over the next 2 hours.

Perenco Dimlington Terminal unplanned shutdown, Plant restart ongoing

Unavailable Capacity
2.2mcm/d
Available Capacity
2mcm/d
Technical Capacity
2.2mcm/d
Further Information