Impacted time period

Tuesday 27th October 2026 at 8:00pm to Thursday 29th October 2026 at 12:00pm

Elgin Franklin gas export has restarted and flows through Bacton SEAL will commence at 23:00hrs. Ramp up will continue overnight and into the course of gas-day 29th October.

Unavailable Capacity
0.6mcm/d
Available Capacity
3.8mcm/d
Technical Capacity
4.4mcm/d