Scheduled time period
Monday 20th January 2020 at 6:00am to Wednesday 22nd January 2020 at 12:00pmCulzean has restarted. A slow ramp up will commence over the next 24 hours.
Unavailable Capacity
91GWh/d
Available Capacity
34GWh/d
Technical Capacity
125GWh/d