Scheduled time period

Monday 20th January 2020 at 6:00am to Wednesday 22nd January 2020 at 12:00pm

Culzean has restarted. A slow ramp up will commence over the next 24 hours.

Unavailable Capacity
91GWh/d
Available Capacity
34GWh/d
Technical Capacity
125GWh/d