This is not the latest revision of this event. Please click here to see the latest update.

Scheduled time period

Thursday 27th August 2020 at 6:00am to Friday 4th September 2020 at 6:00am

These are the latest shutdown dates and are subject to change. There will be a period of reduced rates for a few days either side of the shutdown as production ramps down & restarts

Planned gas production field unavailability at Greater Britannia Area

Unavailable Capacity
7mcm/d
Available Capacity
0mcm/d
Technical Capacity
7mcm/d
Further Information