Scheduled time period

Friday 3rd September 2021 at 6:00am to Friday 24th September 2021 at 6:00am

Perenco Dimlington Terminal Offline due to planned maintenance activities onshore and offshore from 03/09/2021. Onshore elements are expected to conclude on the 17th September allowing a partial return to production (some 70-90mmscf estimate) during the final week of the REMIT post.

Perenco Dimlington Terminal reduced Throughput

Unavailable Capacity
5.5mcm/d
Available Capacity
0mcm/d
Technical Capacity
5.5mcm/d