Scheduled time period

Saturday 23rd September 2023 at 5:00pm to Saturday 23rd September 2023 at 6:30pm

Reduced Perenco Dimlington terminal gas export due to planned maintenance activities. Initial ramp down on 21/09/23 06:00hrs of 0.5MCM/d, followed by further reduction on 22/09/23 06:00hrs of 4.1MCM/d. Ramp up expected to commence 24/09/23 06:00hrs. Preparations are currently underway to resume export with available offshore production. Full production not yet available.

Perenco Dimlington reduced throughput due to planned maintenance activities.

Unavailable Capacity
2.8mcm/d
Available Capacity
1.65mcm/d
Technical Capacity
1.65mcm/d