This is not the latest revision of this event. Please click here to see the latest update.

Scheduled time period

Friday 14th June 2024 at 6:00am to Monday 1st July 2024 at 6:00am

Offshore has commenced taking wells offline prior to the terminal coming offline prior to 06:00hrs gas day 14th. All production will be shutin by 0600hrs. Reduced Perenco terminal throughput due to onshore and offshore maintenance. Partial production restart 06:00 28/06/2024, with remaining production restart 06:00 01/07/2024. Reminder, the Perenco Dimlington Terminal Annual maintenance shutdown will commence as planned from 06:00hrs 14th June

Planned maintenance.

Unavailable Capacity
4.9mcm/d
Available Capacity
0mcm/d
Technical Capacity
4.9mcm/d