Scheduled time period
Friday 14th June 2024 at 6:00am to Wednesday 3rd July 2024 at 1:50pmThere is a potential of a partial return to production during gas day 27th June. 21:05hrs 27th. Export to the NTS commenced with the planned partial return to production. Offshore has commenced taking wells offline prior to the terminal coming offline prior to 06:00hrs gas day 14th. All production will be shutin by 0600hrs. Reminder, the Perenco Dimlington Terminal Annual maintenance shutdown will commence as planned from 06:00hrs 14th June Reduced Perenco terminal throughput due to onshore and offshore maintenance. Partial production restart 06:00 28/06/2024, with remaining production restart 06:00 01/07/2024. Production offshore continues to increase with further expected during gas day 3d July. Annual shutdown now complete, and production resuming steadily.
Planned maintenance.
Related Remits
Below is a list of the other remits that belong to the same event as the remit above.
Scheduled time period
Friday 14th June 2024 at 6:00am to Wednesday 3rd July 2024 at 12:00pmThere is a potential of a partial return to production during gas day 27th June. 21:05hrs 27th. Export to the NTS commenced with the planned partial return to production. Offshore has commenced taking wells offline prior to the terminal coming offline prior to 06:00hrs gas day 14th. All production will be shutin by 0600hrs. Reminder, the Perenco Dimlington Terminal Annual maintenance shutdown will commence as planned from 06:00hrs 14th June Reduced Perenco terminal throughput due to onshore and offshore maintenance. Partial production restart 06:00 28/06/2024, with remaining production restart 06:00 01/07/2024. Production offshore continues to increase with further expected during gas day 3d July.
Planned maintenance.
Scheduled time period
Friday 14th June 2024 at 6:00am to Wednesday 3rd July 2024 at 6:00amThere is a potential of a partial return to production during gas day 27th June. 21:05hrs 27th. Export to the NTS commenced with the planned partial return to production. Offshore has commenced taking wells offline prior to the terminal coming offline prior to 06:00hrs gas day 14th. All production will be shutin by 0600hrs. Reminder, the Perenco Dimlington Terminal Annual maintenance shutdown will commence as planned from 06:00hrs 14th June Reduced Perenco terminal throughput due to onshore and offshore maintenance. Partial production restart 06:00 28/06/2024, with remaining production restart 06:00 01/07/2024.
Planned maintenance.
Scheduled time period
Friday 14th June 2024 at 6:00am to Tuesday 2nd July 2024 at 6:00pmThere is a potential of a partial return to production during gas day 27th June. 21:05hrs 27th. Export to the NTS commenced with the planned partial return to production. Offshore has commenced taking wells offline prior to the terminal coming offline prior to 06:00hrs gas day 14th. All production will be shutin by 0600hrs. Reminder, the Perenco Dimlington Terminal Annual maintenance shutdown will commence as planned from 06:00hrs 14th June Reduced Perenco terminal throughput due to onshore and offshore maintenance. Partial production restart 06:00 28/06/2024, with remaining production restart 06:00 01/07/2024.
Planned maintenance.
Scheduled time period
Friday 14th June 2024 at 6:00am to Monday 1st July 2024 at 6:00amThere is a potential of a partial return to production during gas day 27th June. 21:05hrs 27th. Export to the NTS commenced with the planned partial return to production. Offshore has commenced taking wells offline prior to the terminal coming offline prior to 06:00hrs gas day 14th. All production will be shutin by 0600hrs. Reduced Perenco terminal throughput due to onshore and offshore maintenance. Partial production restart 06:00 28/06/2024, with remaining production restart 06:00 01/07/2024. Reminder, the Perenco Dimlington Terminal Annual maintenance shutdown will commence as planned from 06:00hrs 14th June
Planned maintenance.
Scheduled time period
Friday 14th June 2024 at 6:00am to Monday 1st July 2024 at 6:00amThere is a potential of a partial return to production during gas day 27th June. Offshore has commenced taking wells offline prior to the terminal coming offline prior to 06:00hrs gas day 14th. All production will be shutin by 0600hrs. Reduced Perenco terminal throughput due to onshore and offshore maintenance. Partial production restart 06:00 28/06/2024, with remaining production restart 06:00 01/07/2024. Reminder, the Perenco Dimlington Terminal Annual maintenance shutdown will commence as planned from 06:00hrs 14th June
Planned maintenance.
Scheduled time period
Friday 14th June 2024 at 6:00am to Monday 1st July 2024 at 6:00amOffshore has commenced taking wells offline prior to the terminal coming offline prior to 06:00hrs gas day 14th. All production will be shutin by 0600hrs. Reduced Perenco terminal throughput due to onshore and offshore maintenance. Partial production restart 06:00 28/06/2024, with remaining production restart 06:00 01/07/2024. Reminder, the Perenco Dimlington Terminal Annual maintenance shutdown will commence as planned from 06:00hrs 14th June
Planned maintenance.
Scheduled time period
Friday 14th June 2024 at 6:00am to Monday 1st July 2024 at 6:00amReduced Perenco terminal throughput due to onshore and offshore maintenance. Partial production restart 06:00 28/06/2024, with remaining production restart 06:00 01/07/2024. Reminder, the Perenco Dimlington Terminal Annual maintenance shutdown will commence as planned from 06:00hrs 14th June
Planned maintenance.
Scheduled time period
Friday 14th June 2024 at 6:00am to Monday 1st July 2024 at 6:00amReduced Perenco terminal throughput due to onshore and offshore maintenance. Partial production restart 06:00 28/06/2024, with remaining production restart 06:00 01/07/2024.
Planned maintenance.