Impacted time period
Friday 27th March 2026 at 8:00am to Monday 30th March 2026 at 6:00amElgin Franklin restart process under way. It's forecast that there will be gas export later this gas day.
Unavailable Capacity
4.8mcm/d
Available Capacity
0mcm/d
Technical Capacity
4.8mcm/d