This is not the latest revision of this event. Please click here to see the latest update.

Impacted time period

Sunday 16th August 2026 at 9:00pm to Monday 17th August 2026 at 1:30pm

PUK Dimlington throughput cessation Revised restart time frame, further updates to follow on progress. Works completed, awaiting a return to export.

unplanned onshore maintenance

Unavailable Capacity
4mcm/d
Available Capacity
0mcm/d
Technical Capacity
4mcm/d