Impacted time period

Sunday 16th August 2026 at 9:00pm to Monday 17th August 2026 at 2:05pm

PUK Dimlington throughput cessation Revised restart time frame, further updates to follow on progress. Works completed, awaiting a return to export. Forward flows from 14:05

unplanned onshore maintenance

Unavailable Capacity
0mcm/d
Available Capacity
4mcm/d
Technical Capacity
4mcm/d